CMMS Five Year Plan
From WeKey
Jump to navigationJump to searchThis is both an historical record and a work in progress.
Only the latest version should be under construction:
CMMS Five Year Plan - 2006
CMMS Five Year Plan - 2008
Link to Wiki for the current Full TRIUMF 5YP
Schedule of a typical TRIUMF 5YP:
- 2007-Dec-01: Writing begins in earnest on technical sections.
- 2008-Feb-01: First full draft of Part 1, Part 2, and Part 3 are complete
- 2008-Mar-01: Informal (internal?) review of technical sections is completed Stand-alone website is commissioned
- 2008-Mar-15: Draft of Executive Summary and Summary is prepared.
- 2008-Apr-15: Board and other provide final guidance Stand-along publications are field tested
- 2008-May-01: Report text is nearly finalized and enters composition & layout
- 2008-May-15: ACOT provides additional input
- 2008-Jun-15: Report is frozen.
- 2008-Jul-15: Send full report to Peer Review Committee.
- 2008-Sep-15: International Peer Review Committee provides report.
- 2008-Oct-01: Report is really, really frozen
- 2009-Feb-01: 5YP document presented to NRC, NRC Council